Question Bank with Model Answers
CPM & Scheduling
What is total float and how is it calculated?
TF = LS − ES (or LF − EF). It is the amount an activity can slip without delaying project completion. Zero-float activities form the critical path.
Explain the difference between free float and total float.
Free float is slippage available without delaying the successor’s early start (FF = ES(succ) − EF); total float is slippage available without delaying the project. FF ≤ TF always.
What causes negative float and what do you do about it?
A constraint (e.g. contractual finish) earlier than the network can achieve. Response: recovery — re-sequence, crash critical activities, or formally re-baseline with approval.
Retained logic vs progress override in P6 — when does it matter?
With out-of-sequence progress: retained logic keeps remaining work behind incomplete predecessors (conservative); progress override lets it proceed (aggressive). It can swing the critical path materially.
How do you check the quality of a schedule you receive?
DCMA-14 style checks: missing logic, dangles, leads/lags abuse, constraints count, high float, negative float, long durations, invalid dates, resource loading, critical path integrity.
Earned Value
Your CPI is 0.85 at 30% complete. What does it mean and what do you do?
You earn ₹0.85 per rupee spent — a 15% cost inefficiency. At 30% this rarely self-corrects: identify variance drivers by work package, quantify EAC (BAC/CPI), brief the sponsor, and act on the drivers or re-baseline.
Difference between EAC = BAC/CPI and EAC = AC + (BAC − EV)?
The first assumes current cost performance continues (systemic variance); the second treats variance as one-off and remaining work per plan. Choose based on the cause of variance.
What is TCPI and why do sponsors care?
Efficiency needed on remaining work to hit a target: (BAC−EV)/(BAC−AC). Above ~1.10 is generally unachievable — it tells the sponsor whether the budget promise is still credible.
How do you measure physical percent complete objectively?
Rules of credit tied to measurable outputs: quantities installed vs total, weighted milestones per deliverable, 0/100 or 50/50 for short activities. Never unverified assessor opinion.
Delay & Claims
Which delay analysis method would you use during a live project and why?
Time Impact Analysis — insert the delay fragnet into the current updated programme and measure movement of completion. It is prospective, contemporaneous, and preferred by most protocols for EOT assessment.
What is concurrent delay?
Employer and contractor delay events affecting the critical path in the same window. Common treatment (English-law influenced): time granted, money not — but it varies by jurisdiction and contract.
What records win claims?
Contemporaneous ones: updated programmes, daily reports with manpower/locations, photos, correspondence, notices served on time, and minutes. Reconstructed narratives lose to records.
Behavioural / Situational
The PM asks you to hide a slippage in the monthly report. What do you do?
Report accurately — integrity is non-negotiable in controls. Offer to pair the bad news with a recovery plan and options; escalate through the dotted line (PMO/controls manager) if pressured.
Site says the schedule is "just paperwork". How do you get buy-in?
Make it useful to them: build it around their execution plan, keep look-aheads short and practical, deliver answers fast (what-if runs), and give them credit when the plan works.
How do you handle two seniors giving conflicting priorities?
Surface the conflict transparently with the impact of each option (time/cost/resource), ask for a joint decision, and record it. Never silently pick one.
Indicative Salary Guide
Broad market ranges — actuals vary by city, sector and company tier. Updated periodically.
| Role | India — Tier 2 / mid firms | India — metros / top firms | Gulf (indicative) |
|---|---|---|---|
| Planning Engineer (0–3 yrs) | ₹4–8 LPA | ₹8–15 LPA | AED 8–15k/mo |
| Senior Planning Engineer (4–8 yrs) | ₹8–16 LPA | ₹15–28 LPA | AED 15–25k/mo |
| Project Controls Lead (8–12 yrs) | ₹16–30 LPA | ₹28–45 LPA | AED 25–40k/mo |
| Planning / Controls Manager (12+ yrs) | ₹25–45 LPA | ₹40–70 LPA | AED 35–55k/mo |
| Delay Analyst / Claims Consultant | ₹12–30 LPA | ₹25–60 LPA | AED 25–50k/mo |
| Project Manager (PMP, 8+ yrs) | ₹18–35 LPA | ₹30–60 LPA | AED 30–50k/mo |
Resume Tips for PM Roles
Lead with tools + sectors
First line after your name: "Planning Engineer — Primavera P6, MS Project | Construction & Oil & Gas". Recruiters filter by these keywords.
Quantify your projects
Not "worked on metro project" but "planned ₹850 Cr elevated metro package: 4,200-activity P6 programme, 14 monthly EOT-free updates".
Show controls outcomes
Recovered float, claims supported, forecast accuracy — outcomes beat responsibilities.
One page per 8 years
Two pages max. Cut early-career detail as you grow.
Mirror the JD keywords
ATS systems match literally: if the ad says "QSRA" and you write "quantitative risk", you may not surface.
Hiring planning & controls talent?
Post roles to our community of planning engineers and PM professionals — free during launch.
Post a Job