How to Estimate Project Cost
A defensible budget starts with a sound estimate. Combine techniques for a number you can stand behind.
For the full concept, see Cost Estimation.
Steps
- Break down the work so you cost pieces, not the whole at once.
- Choose techniques: analogous (fast), parametric (data-driven), bottom-up (accurate).
- Use three-point estimates on uncertain items: (O + 4M + P) Γ· 6.
- Add direct and indirect costs, then contingency for known risks.
- Add management reserve for unknown-unknowns, controlled by management.
- Document assumptions so the estimate can be challenged and refined.