Two network scheduling techniques that are usually combined rather than chosen between.

CPMPERT
DurationsSingle (deterministic)Three-point (probabilistic)
FocusLongest path, floatUncertainty and expected time
OriginConstruction/maintenanceR&D (Polaris programme)
OutputCritical path, datesExpected time, variance
Use together?Yes β€” network + pathYes β€” supplies the estimates

The verdict

Use PERT’s three-point estimates to handle uncertainty, then CPM to find the critical path through the same network.